Facility: Brier
Creek Country Club
Cary NC
Reference: Jim Van Buren, General Manager
Lee Honeycutt, Senior Land Development Manager
Completion Date: Spring of 2005 for Phase II
Aquatic facility narrative:
General
attributes:
1. This
was a two phase project
a. Phase
one consisted of the combination pool, the wading pool, pool equipment and
chemical storage rooms adequately sized for adding a competition pool
b. Phase two
consisted of adding another pool which, based on the developing demographics,
was design as a play pool
2. Scope
of design by Pool Design Consultants
a. Combination
pool consisting of competition, leisure, and water slide component
b. Wading
pool
c. Play
pool as part of Phase II
d. Pool
equipment room and chemical storage room hydraulics
e. In
conjunction with the owner, Pool Design Consultants, Inc. provided project
management advise for the owner.
3. Scope
of design by the architect during phase one
a. Facilities
b. Deck
c. Fence
d. Shelter
e. Pool
equipment building
The
multiple use aquatic facility was designed per the following design criteria:
1. NC Department of Environment
and Natural Resources T15A: 18A .2500 NC DENR, DEH Environmental Health
Services March 1, 2004 SECTION .2500 -
PUBLIC SWIMMING POOLS
2. ANSI/NSPI 1 Current edition
at the time of design
The multiple use aquatic facility was designed for the
following activities:
1.
Competitive swimming events
2.
Large deck area to accommodate multiple swim team events
and allow for high volume use
3.
Aerobics
4.
Leisure activities
5.
ADAAG access
6.
Slide feature
7.
Water features using both a wading pool and play pool
The multiple use aquatic facility was designed for the
operational attributes:
2.
Institutional quality hydraulic systems
3.
Automated backwash controls
4.
Automated water level control systems